Supply chain optimisation cuts changeover time by 35%
2nd April 2025 | 1 min read


The Challenge
The intricate nature of aerospace supply chains often poses considerable challenges to maintaining efficiency and productivity. A tier 1 aircraft component manufacturer aimed to enhance efficiency and operational effectiveness at its UK site through expert supply chain optimisation. The company engaged Unipart to provide performance improvement recommendations.
The focus was on their Computer Numerical Control (CNC) processes. These processes needed up to 1.5 hours to change over for every 15 hours of use. The client wanted to reduce this changeover time by 30%.